St. George Greek Orthodox Church
87 Ashley Boulevard ~ New Bedford, MA 02746 ~ Tel: (508) 996-5913

New Building
January 14, 2009:
  • Our utility pole was installed this week.
  • Last week, the gas line from our building was tunneled under our parking lot, up the hill and
    under Cross Road and connected to the main gas line under the street. This is critical for
    interior winter construction.
  • The roof shingles on the administration section have been installed.
  • The siding is complete on the adminstration section and partially on the coffee hall.
  • Plumbing started yesterday.
  • All the rooms are framed.
  • All windows installed.
  • Bufftree is in the process of designing the altar and the iconostasis.
  • We are contemplating using our current pews for the new church.  We are in the process
    of obtaining prices on how much it would cost to refurbish them.
  • Click here to see our latest art rendering.
  • If you have any questions or concerns, please contact the building committee.
  • Important meeting Tuesday, January 27th to discuss flooring and interior door options.
    David Correia from Bufftree will be attending this meeting.

August 22, 2007:
  • A purchase and sale agreement was signed by our buyers.
  • An agreement was signed with Bufftree Construction Company to begin the land
    engineering of our future site at Cross Road in Dartmouth, MA.

August 19, 2007: Notes from the general assembly.
  • The building of our new church will be in two phases. The new facility, under phase one, is
    approximately 6,800 sq. ft., our current church is approximately 5,200 sq. ft. The
    temporary church will hold 200 people and the temporary hall will hold 70 people, seated.
    Click here to view the floor plan. You will need Adobe reader, click here to download.
  • The parishoners overwhelmingly approved to sell and vacate our church within six months.
  • It was announced that Metropolitan Methodios will conduct the Divine Liturgy on
    November 11, 2007 and lead us in the ground breaking of our new facility at Cross Road.
    Festivities for that weekend are being planned.

May 10, 2007: Click here to view the letter read during general assembly.